Following important points to know while planning a house at Delhi :-

1. Road level in front of plot is taken as zero level for all levels in the building.Plinth level is kept at least one ft. higher ie.at level 1.0 or higher.Total height of the building allowed is 15.0 meters or  49.21 ft. In case of Gurgaon,Total height allowed is 11.00 mts.ie 36.00 ft. & besides basement, GF, Ist &IInd floor are allowed.

However there are plans to amend the rules in Master plan of Delhi 2021 to raise cap to 17.50 meters.This however would be applicable to only those buildings that go for stilt parking in the ground floor.

2. In Delhi height of habitable room allowed is minimum 9'  maximum 13'

3. Delhi setbacks as per MPD 2021 are:-

 

Plot size(in Sqm)

Minimum Setbacks (in ft)

 

Front

Rear

Side(1)

Side(2)

Below 100

0

0

0

0

Above 100 and upto 250

10

0

0

0

Above 250 and upto 500

10

10

10

0

Above 500 and upto 2000

20

10

10

10

Above 2000 and upto 10000

30

20

20

20

Above 10000

50

30

30

30

4.  Basement below zero level/stilt for parking/G.floor/F.floor/2nd.floor/3rd.floor are allowed in 15.00 mt.

5.Following table shows FAR  (Floor Area Ratio) for different areas of plots.

As per the master plan 2021 the FAR is as follows. Refer-

http://www.indianrealestateforum.com/usercp.php 

Residential Plotted Development 
Sl. No. - Area of the plot(sqm) - Maximum ground coverage % - Maximum FAR - Maximum height in metres 
1 Below 32 90 350 15 - 
2 Above 32 to 50 90 350 15 
3 Above 50 to 100 90 350 15 
4 Above 100 to 250 75 300 15 
5 Above 250 to 500 75 225 15 
6 Above 500 to1000 50 150 15 
7 Above 1000 to1500 40 120 15

FAR=Total covered area of all floors/Plot Area *100

Basement is not included in finding FAR.

6.   Digging of basement & foundation

            In stead of manual labour , JCB earth excavation machines are used for cheaper & expedicious working. Charges vary from Rs.750/-per 100 cft. to Rs.1000/-per 100 cft . for excavation  & cartage of earth by trucks.

            After final digging of earth ,anti-termite  process is taken up by experts. This should be got done very attentively & in personal supervision .If not properly done, it results in permanent headache & expenses.

If on two sides of plot, buildings exist, & plot size is say 30’*60’ .  2meters = 6’7” space is left while digging basement, for security of buildings .Besides 10’ front setback 5’ in the back is required to be left as per authorities.

7. ARCHEOLOGICAL NORMS TO FOLLOW IN DELHI

Proximity to a centrally-protected monument has become a bane for residents wanting to construct new properties or modify the existing ones. The National Monuments Authority (NMA), factoring in the concerns, has recently permitted new constructions in regulated zones up to a height of 18 metres. 


This means a four-storey building—complete with a basement, stilt and a rooftop structure—can come up beyond 100 metres of any of the 174 monuments under the Archaeological Survey of India (ASI).